 ROAD AND LANE CLOSURES SCHEDULED FOR AUGUST 20 – AUGUST 26

 

MONTEREY COUNTY – Here are the major scheduled road and lane closures for Monterey County from Sunday, August 20 through Saturday, August 26 – newest information is in red. Please keep in mind that construction work is weather-dependent.

Highway 1 Storm Repair Along the Big Sur Coast

Due to multiple active slides and bridge replacement, State Route 1 is now closed between Salmon Creek (Mon PM 2.25) and Gorda, and at the Pfeiffer Canyon Bridge construction zone. Access between Gorda and Big Sur is via Nacimiento Fergussion Road.

Highway 1 – Big Sur: August 21 – August 25

  • Daytime bridge work along Highway 1 at the Little Sur River Bridge from 8 a.m. to 3 p.m.

Highway 1 – Carmel Highlands: August 21 – August 25

  • Daytime tree work along Highway 1 between Garrapata State Park and Fern Canyon Road from 9 a.m. to 2 p.m. 
  • Traffic Control with flagging
  • Motorists can expect delays of approximately 10 minutes.

Holman Highway 68 Roundabout: August 21 – August 25

  • Daytime landscaping and sign installation.
  • Occasional shoulder closures and flagging.

Highway 101 – Salinas: August 21 – August 23

  • Daytime maintenance work will result in the closure of the northbound Highway 101 off-ramp to Sanborn Road from 9 a.m. to 2 p.m.

Highway 101 – Prunedale: August 21 – August 23

  • Daytime k-rail installation along southbound Highway 101 between Blackie Road and Ralph Lane from 9 a.m. to 2 p.m. 

Highway 218/Canyon Del Rey: August 21 – August 25

  • Daytime vegetation spraying along Canyon Del Rey Boulevard between Highway 1 and Highway 68 from 9 a.m. to 2 p.m.