Cone Zone Report

Date:              Friday, September 6, 2019

District:         05 – Santa Barbara, San Luis Obispo, Monterey, San Benito, and Santa Cruz Counties

Contact:        Theresa Wright, (TAMC)

Phone:          (831) 775-0903

FOR IMMEDIATE RELEASE

TAMC CONE ZONE REPORT

ROAD AND LANE CLOSURES SCHEDULED FOR September 8 – September 14

 

MONTEREY COUNTY – Here are the major scheduled road and lane closures for Monterey County from Sunday, September 8 through Saturday, September 14 – newest information is in red. Please keep in mind that construction work is weather-dependent.

 

Highway 1: Bixby Creek Bridge – Hurricane Point: Sept. 9 – Sept. 13
One – way traffic controls will be in place on northbound and southbound Highway 1 between Bixby Creek Bridge and Hurricane Point for slope repair work along the highway from 6 a.m. to          3 p.m.

Highway 68: Pacific Grove – Monterey: September 8 – September 13
One nighttime lane closure and one-way traffic controls will be in place along eastbound and westbound Highway 68 between Piedmont Avenue and Highway 1 for drainage work in the evenings from 8 p.m. to 6 a.m.

Highway 68: Bit Road – Olmsted Road, Monterey: Sept. 8 – Sept. 12
Nighttime lane closure and one-way traffic controls will be in place along eastbound and westbound Highway 68 between Bit Road and Olmsted Road in Monterey for utility work from 8 p.m. to   5 a.m.

Highway 68: Bit Road – Laureles Grade, Monterey: Sept. 9 – Sept. 13
One nighttime lane closure and one-way traffic controls will be in place along eastbound Highway 68 between Bit Road and Laureles Grade in Monterey for tree removal work, from 8 p.m. to         5 a.m.

Highway 68: Pajaro Street – Soledad Street, Salinas: September 9 – September 13
One lane closure will occur along eastbound Highway 68 between Pajaro Street and Soledad Street in Salinas for utility work, from 9 a.m. to 3:30 p.m.

Highway 101: Alta Street/Old Stage Road – Little Bear Creek Bridge, Salinas: Sept. 8 – 13
Nighttime lane closures, including the eastbound East Market Street on/off-ramps, will occur along northbound and southbound Highway 101 between Alta Street/Old Stage Road and Little Bear Creek Bridge in Salinas for paving work on the roadway and ramps from 9 p.m. to 6 a.m.

Highway 101: Camp Roberts: Now – October 11
One long-term on-ramp closure will occur along southbound Highway 101 at Camp Roberts for paving work from 6 a.m. to 2 p.m.

Highway 101: San Ardo – San Lucas: Now – December 31
One long-term lane closure will occur along northbound and southbound Highway 101 between the Paris Valley Road overcrossing and the Rancho undercrossing for grinding and paving work.

Highway 101: Wild Horse – First Street, King City: Now – January 2020
One long-term lane closure will occur along northbound and southbound Highway 101 between Wild Horse Road and First Street for roadway excavation work from 5:00 a.m. to 12:00 p.m.

Highway 101: Highway 183 (Main Street) Salinas:  Now – September 24
There will be a long-term nighttime closure of the on/off ramps at southbound Highway 101 and northbound Highway 183 (North Main Street) in Salinas for paving work from 7 p.m. to 12 p.m.

Highway 183: Salinas Street – Lincoln Avenue, Salinas: September 9 – September 13
One lane closure will occur along northbound Highway 183 (West Market Street) between Salinas Street and Lincoln Avenue for utility work from 8:00 a.m. to 3:00 p.m.

# # #

Caltrans and the CHP remind motorists to drive safely through work construction zones.